Elsta Sp. z o.o. on behalf of the general contractor - MHPSE - it was tasked with making cable routes and laying cables on the construction site of a 1075 MW unit. It is currently the largest such project in Europe, with a value of over PLN 6.3 billion. The cable works were to be performed from December 2015 to July 2017. The project did not really start until April 2016, when the first work fronts were secured. In July 2017, the project is nearing completion - in December, the unit was put into operation.